DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule for the US 301 Mainline Project during the week of May 30, 2018.

Written on: May 25th, 2018 in US 301 Project Updates US301

Wednesday May 30, 2018 and Thursday, May 31, 2018: Dayshift

Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 9 AM until 3 PM.

Continue roadway widening activities along southbound US 13. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 9 AM until 2 PM.

Continue roadway widening activities along northbound US 13. Motorists should anticipate a single right lane closure along northbound US 13 prior to the Free Ramp to SR 1 from 9 AM until 2 PM.

Continue bridge construction activities along Bunker Hill Road. Motorists should anticipate an eastbound or westbound lane closure on Bunker Hill Road, west of Choptank Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 AM until 5 PM.

Continue bridge construction activities on Boyds Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 AM until 3 PM.

Thursday, May 31, 2018: Nightshift

Continue toll plaza construction activities along northbound SR 1. Motorists should anticipate a single left lane closure along northbound SR 1 from Boyds Corner Road to the Toll Plaza including the closure of both High Speed E-ZPass Lanes along northbound SR 1 from 7 PM until 5 AM.

Continue toll plaza construction activities along southbound SR. Motorists should anticipate a single left lane closure along southbound SR 1 from the Roth Bridge to the Boyds Corner Road including the closure of both High Speed E-ZPass Lanes along northbound SR 1 from 9 PM to 7 AM.

Detours and Roadway Closures

Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US 13. Traffic accessing Port Penn Road from southbound US 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US 13 will follow US 13 to the traffic signal at the free ramp to northbound State Route 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect until June 2018 after the intersection is reconstructed and the new traffic signal becomes operational.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to Boyd’s Corner Road (SR 896) and turn right, follow Boyd’s Corner Road to Jamison Corner Road and turn right, follow Jamison Corner Road through the roundabout and back to Hyetts Corner Road.

 




+