Written on: April 27th, 2018 in US 301 Project Updates US301
Monday, April 30, 2018 through Thursday, May 3, 2018 – Dayshift
Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 9 a.m. until 3 p.m.
Continue roadway widening activities along southbound US 13. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 9 a.m. until 2 p.m.
Continue roadway widening activities along northbound US 13. Motorists should anticipate a single right lane closure along northbound US 13 prior to the Free Ramp to SR 1 from 9 a.m. until 2 p.m.
Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyd’s Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 p.m.
Strawberry Lane is anticipated to re-open to traffic during the week, weather depending.
Sunday, April 29, 2018 – Nightshift
Continue bridge construction activities along northbound SR 1. Motorists should anticipate periodic rolling road blocks along northbound SR 1 between the Biddles Toll Plaza and Roth Bridge from 10 p.m. until 4 a.m.
Monday, April 30, 2018 and Tuesday, May 1, 2018 – Nightshift
Continue bridge construction activities along SR 1. Motorists should anticipate periodic rolling road blocks along northbound and southbound SR 1 between the Biddles Toll Plaza and Roth Bridge from 10 p.m. until 4 a.m.
Monday, April 30, 2018 – Nightshift
Continue bridge construction activities along southbound SR 1. Motorists should anticipate a double left lane closure, including the E-ZPass Lane, from 10 p.m. until 5 a.m.
Wednesday, May 2, 2018 – Nightshift
Continue bridge construction activities along northbound SR 1. Motorists should anticipate a double left lane closure, including the E-ZPass Lane, from 10 p.m. until 5 a.m.
Friday, May 4, 2018 – Nightshift
Continue bridge construction activities along southbound SR 1. Motorists should anticipate a double left lane closure, including the E-ZPass Lane, from 10 p.m. until 5 a.m.
Detours and Roadway Closures
Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US 13. Traffic accessing Port Penn Road from southbound US Route 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US Route 13 will follow US Route 13 to the traffic signal at the free ramp to northbound State Route 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect until June 2018 after the intersection is reconstructed and the new traffic signal becomes operational.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyd’s Corner Road (SR 896) and turn left, follow Boyd’s Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyett’s Corner Road should turn right at US 13, follow US R 13 to Boyd’s Corner Road (SR 896) and turn right, follow Boyd’s Corner Road to Jamison Corner Road and turn right, follow Jamison Corner Road through the roundabout and back to Hyetts Corner Road.