SR141/I95 Ramp Improvement Project
October 9, 2017
The contractor, Mumford & Miller Inc., have begun to clear vegetation and widening the roadway on SR141 southbound on the closed side of the roadway. They are demolishing the existing SR141 southbound and northbound bridges, constructing foundations and building piers for the new bridges. They have also begun construction of the Exit 5 ramp from I295 northbound to SR141 northbound. They are working on installing utility infrastructure through the SR141 and I95 northbound corridor.
LANE CLOSURES:
Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9a.m. to 3p.m., Monday thru Friday.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until December 2017. Motorists traveling to northbound SR141/Newport should use Exit 5.