The contractor, Mumford & Miller Inc., will continue placing fill for widening I-95 northbound acceleration lane from SR 141. They will continue to form and pour barrier for SR 141 northbound. They are working on installing utility infrastructure and constructing overhead sign structures through the SR 141 and I-95 northbound corridor. The contractor is reconstructing the ramp for Exit 3A, northbound SR141 to northbound I-95. They are installing a stormwater drainage system on this ramp.
There will be multiple lane closures on I-95 and I-295 during the hours of 8PM to 5AM.
Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late October 2017. northbound SR141/Newport should use Exit 5.
Ramp Exit 3A (NB SR 141 to NB I-95) will be closed until late August 2017. Motorists traveling on SR 141 northbound will follow detour signs to US 13 northbound to I-295 to I-95 northbound.