DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the week of April 17.

Written on: April 13th, 2017 in US 301 Project Updates US301

Monday, April 17 through Thursday, April 20

Continue bridge construction activities along SR 1. Motorists should anticipate a single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m.

 Monday, April 17 through Friday, April 21

Continue roadway widening activities along Summit Bridge Road. Motorists should anticipate northbound or southbound lane closures on Summit Bridge Road, north and south of the Armstrong Corner Road/Marl Pit Road intersection, with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 p.m.

Continue roadway widening activities along Summit Bridge Road. Motorists should anticipate northbound and southbound lane shifts on Summit Bridge Road north and south Armstrong Corner/Marl Pit Road with traffic getting through the work zone utilizing a flagging operation by construction personnel from 7 a.m. until 9 a.m. AND 3 p.m. until 5 p.m.

Continue placement of Temporary Concrete Traffic Barrier for Phase 2 work between Old Hyetts Corner Road and Port Penn Road. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Old Hyetts Corner Road and Port Penn Road from 9 a.m. until 3 p.m.

Continue installing light pole bases along the northbound shoulder of US 13 between Old Hyetts Corner Road and Port Penn Road. Motorists should anticipate a northbound right shoulder closure along US 13 between Old Hyetts Corner Road and Port Penn Road from 9 a.m. until 3 p.m.

Continue dirt hauling and bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road (SR 896) west of Jamison Corner Road from 8 a.m. until 4 p.m.

Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7 a.m. until 5 p.m.

Begin temporary line striping and saw cutting for Phase 2 work between Old Hyetts Corner Road and Port Penn Road. Motorists should anticipate a single left lane or right lane on northbound US 13 between Old Hyetts Corner Road and Port Penn Road from 9 a.m. until 3 p.m.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road.  Motorists traveling eastbound on Hyett’s Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road (SR 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.

Middle Neck Road is closed at US 301. Motorists wishing to access Middle Neck Road from US 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.

Strawberry Lane is closed to traffic at US 301. Motorists wanting to access the east side of Strawberry Lane from US 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from US 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.




+