Monday, February 20, through Thursday, February 23
Continue bridge construction activities along SR 1. Motorists should anticipate single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m.
Tuesday, February 21, 2017 motorists should anticipate a single lane closure along southbound SR 1 with periodic traffic drags to move equipment from 10 p.m. until 5 a.m.
Monday, February 20 through Friday, February 24
Continue dirt hauling and bridge construction activities on Boyd’s Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8 a.m. until 4 p.m.
Continue dirt hauling and other construction activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons Way with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 a.m. until 4 p.m.
Continue dirt hauling and other construction activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7 a.m. until 5 p.m.
Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7 a.m. until 5 p.m.
Middle Neck Road is closed at U.S. Route 301. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at U.S. Route 301. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.