Written on: February 6th, 2017 in US 301 Project Updates US301
Monday, February 6, 2017 through Thursday, February 9, 2017
Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m.
Begin installing roadway light pole bases. Motorists should anticipate northbound and southbound shoulder closures along U.S. Route 13 between Old Hyetts Corner Road and Port Penn Road from 9:00 a.m. – 3:00 p.m.
Begin installing drainage pipe across U.S. Route 13. Motorists should anticipate left lane or right lane closures along U.S. Route 13 near Old Hyetts Corner Road from 9:00 a.m. to 3:00 p.m.
<strong>
Monday, February 6, 2017 through Friday, February 10, 2017
Continue dirt hauling and bridge construction activities on Boyd’s Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling and other construction activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons Way with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 4:00 p.m.
Continue dirt hauling and other construction activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Middle Neck Roads is closed at U.S. Route 301. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at U.S. Route 301. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (State Route 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (State Route 299) to Wilson Street/Strawberry Lane.