us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: May 5th, 2016 in US 301 Project UpdatesUS301

Monday, May 9, 2016 through Saturday, May 14, 2016

Continue dirt hauling activities along Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Continue excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High School. No lane closures are needed for this construction activity.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 4:00 p.m.


us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: April 29th, 2016 in US 301 Project UpdatesUS301

Monday, May 2, 2016 through Saturday, May 7, 2016

Continue dirt hauling activities along Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Continue excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High school. No lane closures are needed for this construction activity.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Continue hauling activities across Middleneck road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 4:00 p.m.


route-26

Route 26 Update and Anticipated Closures

Written on: April 29th, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.
Monday, May 2, 2016 through Saturday, May 7, 2016
Powell Farm Road and Omar Road will remain closed at SR 26. Motorists are advised to follow
the following posted detour:
Northbound: Powell Farm Road, right onto Burbage Road, left onto SR 17 and end on SR 26.

Southbound: Powell Farm Road, left on Burbage Road, left on SR 17 and back onto SR 26.

Continue to place concrete for sidewalk on Route 26 between West Avenue and the Assawoman
Canal.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between
West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing
a flagging operation by law enforcement and construction personnel from 09:00AM to 5:00PM.
Begin grading for new curb on Route 26 at Powell Farm Road. Motorists should anticipate
eastbound or westbound lane closures on Route 26 at Powell Farm Road with traffic alternating
through the work zone utilizing a flagging operation by law enforcement and construction
personnel from 07:00AM to 5:00PM.
Continue adjusting manhole height on Route 26 between Woodland Avenue and Old Mill Road.
Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes
getting through the work zone utilizing a flagging operation by construction personnel from
07:00AM to 5:00PM


us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: April 22nd, 2016 in US 301 Project Updates

Monday, April 25, 2016 through Saturday, April 30, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Begin excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High school. No lane closures are needed for this construction activity.
Begin dirt hauling activities across Bunker Hill Road. Motorists should anticipate lane closures on Bunker Hill Road near Appoquinimink High School with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.


route-26

Projected construction work for the Route 26 Project

Written on: April 22nd, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.
Monday, April 25, 2016 through Saturday, April 30, 2016
Continue to place concrete for sidewalk on Route 26 between West Avenue and the Assawoman
Canal. Motorists should anticipate eastbound or westbound lane closures on Route 26 between
West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing
a flagging operation by law enforcement and construction personnel from 9:00 a.m. to 5:00 p.m..
Continue milling and paving on Route 26 at Powell Farm Road. Motorists should anticipate
westbound lane closures on Route 26 at Powell Farm Road with traffic alternating through the
work zone utilizing a flagging operation by law enforcement and construction personnel from
7:00 a.m. to 9:00 a.m..
Monday, April 25, 2016 through Friday, May 13, 2016
Powell Farm Road and Omar Road will be closed at SR 26. Motorists are advised to follow the
following posted detour:
Northbound: Powell Farm Road, right onto Burbage Road, left onto SR 17 and end on SR 26.
Southbound: Powell Farm Road, left on Burbage Road, left on SR 17 and back onto SR 26.


us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week

Written on: April 18th, 2016 in US 301 Project Updates

Monday, April 18, 2016 through Saturday, April 23, 2016

Begin dirt hauling activities along Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone from 8:00 p.m. to 6:00 a.m.

Begin excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High school. No lane closures are needed for this construction activity.
Begin dirt hauling activities across Bunker Hill Road. Motorists should anticipate lane closures on Bunker Hill Road near Appoquinimink High School with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.


route-26

Anticipated road closures for Route 26 project

Written on: April 15th, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week.

Monday, April 18, 2016 through Saturday, April 23, 2016

Continue to grade for sidewalk on Route 26 between West Avenue and the Assawoman Canal.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing a flagging operation by law enforcement and construction personnel from 09:00AM to 5:00PM.

Continue milling and paving on Route 26 at Powell Farm Road.

Motorists should anticipate westbound lane closures on Route 26 at Powell Farm Road with traffic alternating through the
work zone utilizing a flagging operation by law enforcement and construction personnel from 07:00AM to 9:00PM.

Continue to grade for swale ditches on Route 26, east of Whites Neck Road.

Motorists should anticipate westbound lane closures on Route 26 at whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00AM to 5:00PM.


us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the week.

Written on: April 13th, 2016 in US 301 Project Updates

Monday, April 11, 2016 through Saturday, April 16, 2016
Begin dirt hauling activities on Hyetts Corner Road. Motorists should anticipate eastbound or westbound lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.
Begin work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone from 8:00 p.m. to 6:00 a.m.


uncategorized

Route 26 Project Update

Written on: April 12th, 2016 in Uncategorized

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week.

Monday, April 11, 2016 through Saturday. April 16, 2016

Continue to grade for sidewalk on Route 26 between West Avenue and the Assawoman Canal.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing a flagging operation by law enforcement and construction personnel from 09:00AM to 5:00PM.

Continue milling and paving on Route 26 between Bethany Crest and Whites Neck Road.

Motorists should anticipate westbound lane closures on Route 26 between Bethany Crest and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 9:00PM.

Complete installation of drainage inlets along Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 at Powell Farm Road with traffic alternating through the work zone utilizing flagging operation by law enforcement and construction personnel from 09:00AM to 5:00PM.


uncategorized

Update for Route 26 Project

Written on: March 24th, 2016 in Uncategorized

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Monday, March 28, 2016

Clubhouse Road will be closed at SR 26 from 9:00AM to 5:00PM. Motorists should follow the posted detour.

Monday, March 28, 2016 through Saturday, April 2, 2016

Continue milling and paving on Route 26 between West Avenue and the Assawoman canal. Motorists should anticipate eastbound lane closures on Route 26 between West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing a flagging operation by law enforcement and construction personnel from 07:00AM to 9:00PM.

Construct a swale ditches and grade for new curb on Route 26 between Bethany Crest and Whites Neck Road. Motorists should anticipate eastbound or westbound lane closures on Route
26 between Bethany Crest and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00AM to 5:00PM.

Continue to complete the construction of swale ditches along SR 26 between Powell Farm Road and Roxana Road. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Powell Farm Road and Roxana Road with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.

Continue to complete drainage grading on Route 26 between Whites Neck Road and Railway Road. Motorists should anticipate westbound lane closures or lane shifts with traffic traveling through the work zone utilizing flagging operation construction personnel from 09:00AM to 5:00PM.

Complete the installation of drainage pipe, inlets and the construction of swale ditches in front of the Lord Baltimore Elementary School. Motorists should anticipate eastbound and westbound lane shifts on Route 26 at Old School Lane with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.





+