us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: June 6th, 2016 in US 301 Project UpdatesUS301

Monday, June 6, 2016 through Friday, June 10, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Continue excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High School. No lane closures are needed for this construction activity.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 4:00 p.m.


route-26

Construction update and anticipated closures for Route 26 project.

Written on: June 2nd, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Tuesday, May 31, 2016 through Thursday, June 2, 2016
Continue grading for new curb and placing concrete for new curb on Route 26 at Powell Farm Road. Motorists should anticipate eastbound or westbound shifts on Route 26 at Powell Farm  Road with both lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.

Continue adjusting manhole height and paving entrances to driveways and businesses on Route 26 between Old Mill Road and Roxana Road. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.

Begin profile milling, wedge and leveling on Route 26 between the Assawoman Canal and Old School Lane. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.