Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during this week.

Written on: June 13th, 2016 in US 301 Project Updates US301

Monday, June 13, 2016 through Friday, June 17, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures along Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility through mid-week. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone. This construction activity is anticipated to be completed on Wednesday, June 15, 2016.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Relocated Bunker Hill Road will be open to traffic between Choptank Road and Merrimac Avenue.