route-26

Anticipated Closures for Route 26

Written on: August 28th, 2015 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Day Shift – Monday, August 31, 2015 through Thursday, September 3, 2015

Continue placing concrete for new curb and side walk between Old School Lane and Woodland Avenue.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 7:00AM to 5:00PM.

Continue placing electrical conduit and associated junction wells for new ITS system at various locations along Route 26. No lane closures are anticipated for this construction activity.

Night Shift – Monday August 24, 2015 through Friday, August 28, 2015

Continue the installation of drainage pipes and associated drainage inlets between West Avenue and Tyler Drive in Ocean View.

Motorists should anticipate eastbound or westbound lane
closures on Route 26 between Tyler Drive and West Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue the installation of drainage pipes and associated drainage inlets between Whites Neck Road and Bethany Crest.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Whites Neck Road and Bethany Crest with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue milling and paving activities between Railway Road and Whites Neck Road.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue placing topsoil around new sidewalk between Old School Lane and Woodland Avenue.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 09:00PM to 8:00AM.

Tidewater Utilities Inc. – Monday, August 31, 2015 through Thursday, September 3, 2015

Continue the installation of new 16 inch water main between Whites Neck Road and Roxana Road.

Motorists should anticipate westbound lane closures on Route 26 between Whites Neck Road and Roxana Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.


route-26

Anticipated Closures and Work for Route 26

Written on: August 20th, 2015 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Day Shift – Monday, August 24, 2015 through Friday, August 28, 2015

Continue placing concrete for new curb and side walk between Old School Lane and Woodland Avenue.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 7:00AM to 5:00PM.

Continue placing electrical conduit and associated junction wells for new ITS system at various locations along Route 26. No lane closures are anticipated for this construction activity.

Night Shift – Monday August 24, 2015 through Friday, August 28, 2015

Continue the installation of drainage pipes and associated drainage inlets between West Avenue and Tyler Drive in Ocean View.

Motorists should anticipate eastbound or westbound lane
closures on Route 26 between Tyler Drive and West Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue the installation of drainage pipes and associated drainage inlets east and west of Whites Neck Road.

Motorists should anticipate eastbound or westbound lane closures on Route 26 at Whites Neck Road with traffic alternating through the work zone and intersection utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Resume milling and paving activities between Grants Avenue and Woodland Avenue.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Grants Avenue and Woodland Avenue with traffic alternating through the work zone and intersections utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Finish grading for new side walk and placement of topsoil around new sidewalk between Old School Lane and Woodland Avenue.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Old School Lane and Woodland Avenue with traffic alternating through the work zone and intersections utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Tidewater Utilities Inc. – Monday, August 24, 2015 through Friday, August 28, 2015

Continue the installation of new 16 inch water main between Railway Road and Whites Neck Road.

Motorists should anticipate westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.


route-26

Anticipated Closures and Work for Route 26

Written on: August 13th, 2015 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Day Shift – Monday, August 17, 2015 through Friday, August 21, 2015

Continue grading for sidewalk between Woodland Avenue and Old School Lane.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 07:00AM to 5:00PM.

Continue placing concrete for new side walk and placement of topsoil around new sidewalk between Old School Lane and Woodland Avenue.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 7:00AM to 5:00PM.

Continue constructing new retaining walls west of Railway Road. Motorists should anticipate eastbound shoulder closures on Route 26 at Railway Road with both travel lanes getting through
the work zone from 07:00AM to 5:00PM.

Continue placing electrical conduit and associated junction wells for new ITS system between Clubhouse Road and Old Mill Road. No lane closures are anticipated for this construction activity.

Continue roadway widening activities between Irons Lane and Roxana Road. No lane closures are anticipated for this construction activity.

Night Shift – Monday August 17, 2015 through Friday, August 21, 2015

Continue the installation of drainage pipes and associated drainage inlets between West Avenue and Town Road in Ocean View. Motorists should anticipate eastbound or westbound lane
closures on Route 26 between Town Road and West Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue the installation of drainage pipes and associated drainage inlets east and west of Roxana Road.

Motorists should anticipate eastbound lane closures on Route 26 at Roxanna Road with traffic alternating through the work zone and intersection utilizing a flagging operation by law enforcement and construction personnel from 09:00PM to 8:00AM.

Tidewater Utilities Inc. – Monday, August 17, 2015 through Friday, August 21, 2015

Continue the installation of new 16 inch water main between Railway Road and Whites Neck Road.

Motorists should anticipate westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.


route-26

Anticipated Closures and Work for Route 26

Written on: August 7th, 2015 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Day Shift – Monday, August 10, 2015 through Friday, August 14, 2015

Continue grading for sidewalk between Woodland Avenue and Old School Lane. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old School Lane and Woodland Avenue with both travel lanes getting through the work zone from 07:00AM to 5:00PM.

Continue placing concrete for new side walk and placement of topsoil around new sidewalk at Old Mill Road. Motorists should anticipate eastbound and westbound lane shifts on Route 26 at Old Mill Road with both travel lanes getting through the work zone from 7:00AM to 5:00PM.

Begin excavating and grading for new retaining walls west of Railway Road.

Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Railway Road and Whites Neck Road with both travel lanes getting through the work zone from 07:00AM to 5:00PM.

Continue placing electrical conduit and associated junction wells for new ITS system at the Route 26 and Roxana Road intersection. No lane closures are anticipated for this construction activity.

Continue roadway widening activities between Irons Lane and Roxana Road. No lane closures are anticipated for this construction activity.

Night Shift – Monday August 10, 2015 through Friday, August 14, 2015

Continue the installation of drainage pipes and associated drainage inlets between West Avenue and Town Road in Ocean View. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Town Road and West Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue the installation of drainage pipes and associated drainage inlets east and west of Roxana Road. Motorists should anticipate eastbound lane closures on Route 26 at Roxanna Road with traffic alternating through the work zone and intersection utilizing a flagging operation by law enforcement and construction personnel from 09:00PM to 8:00AM.

Tidewater Utilities Inc. – Monday, August 3, 2015 through Friday, August 7, 2015

Continue the installation of new 16 inch water main between Railway Road and Whites Neck Road. Motorists should anticipate westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.





+