Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Night Shift – Monday July 20, 2015 through Friday, July 24, 2015

Continue the installation of drainage pipes and associated drainage inlets east of Roxana Road.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Roxana Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue the installation of drainage pipes and associated drainage inlets between Tyler Drive and Riga Road in Ocean View. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Tyler Drive and Riga Drive with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue milling and paving between Grants Avenue and Woodland Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Woodland Avenue and Grants Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue grading for new sidewalk between Old Mill Road and Club House Road. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Old Mill Road and Club House Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue grading for new sidewalk between Grants Avenue and Woodland Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Old School Lane
and Woodland Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.

Continue clean up and placement of topsoil around new sidewalk between Old Mill Road and Cedar Drive. Motorists should anticipate eastbound and westbound lane shifts between Old Mill Road and Cedar Drive with both lanes of traffic traveling through the work zone from 9:00PM to 8:00AM.

Tidewater Utilities Inc. – Monday, July 20, 2015 through Friday, July 24, 2015

Continue the installation of new water main between Club House Road and Railway Road.

Motorists should anticipate westbound lane closures on Route 26 between Club House Road and Railway Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00PM to 8:00AM.





+