Anticipated Work Schedule for May 2

Written on: May 1st, 2015 in Route 26

Route 26 Mainline Improvement Project Scheduled Lane Closures

Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Mainline Improvement Project during the next week. Please note that the first construction activity listed will take place at night.

Monday, May 4, 2015 through Saturday May 9, 2015

Continue milling and paving activities along Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Old School Lane and Woodland Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00PM to 06:00AM.

Continue underground utility relocations in Ocean View. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between West Avenue and Tyler Drive with both lanes getting through the work zone. This lane shift will be in place 24 hours a day, seven days a
week.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Woodland Avenue and Old School Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00AM to 6:00PM.

Continue cleanup and placing topsoil around new sidewalks along Route 26. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between West Avenue and Woodland Avenue with both lanes getting through the work zone from 06:00AM to 6:00PM.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Powell Farm Road and Irons Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00AM to 6:00PM.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Roxana Road (Route 17) and Irons Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00AM to 6:00PM.

Continue placing concrete for new ADA sidewalk ramps along Route 26. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old Mill Road and Grants Avenue with both lanes getting through the work zone from 06:00AM to 6:00PM.

Continue adjusting manholes along Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00AM to 6:00PM.




+