Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next week.
Monday, April 20, 2015 through Saturday April 25, 2015
Continue underground utility relocations in Ocean View. Motorists should anticipate lane shifts on Route 26 between West Avenue and Tyler Drive with both lanes getting through the work zone.
This lane shift will be in place 24 hours a day, seven days a week.
Continue the installation of new drainage pipe and associated drainage inlets along Route 26.
Motorists should anticipate eastbound or westbound lane closures on Route 26 between Woodland Avenue and Old School Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 6:00 a.m. to 6:00 p.m.
Continue placing concrete for new sidewalks along Route 26.
Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Woodland Avenue and West Avenue
with both lanes getting through the work zone from 6:00 a.m. to 6:00 p.m.
Continue grading prior to placing concrete for new sidewalks along Route 26. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old Mill Road and Cedar Drive with both lanes getting through the work zone from 6:00 a.m. to 6:00 p.m.
Continue grading prior to placing concrete for curb and gutter along Route 26.
Motorists should anticipate eastbound and westbound lane closures on Route 26 between Whites Neck Road and Windmill Drive with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00 a.m. to 6:00 p.m.
Begin roadway widening activities between Powell Farm Road and Irons lane. Motorists should anticipate eastbound lane closures on Route 26 between Powell Farm Road and Irons Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 6:00 a.m. to 6:00 p.m.
Relocate and adjust two fire hydrants between Old School Lane and Woodland Avenue. No lane closures are anticipated for this construction activity.