Anticipated work schedule for for week of Feb. 9 – 14

Written on: February 6th, 2015 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next week.

Monday, February 9, 2015 through Saturday, February 14, 2015
Continue the reconstruction of Bridge 3-427 in Millville and Bridge 3-428 in Ocean View.

Motorists are reminded that the detour is in place for this construction activity.

Culvert 3-427 is located in Millville just east of Clubhouse Road between Clubhouse Road and Dukes Drive.

Culvert 3-428 is located just east of Old School Lane and the Lord Baltimore Elementary School.

Through traffic on Route 26 should use the following detours:

Traveling Eastbound – Route 26 to Windmill Drive turn right, to Central Avenue turn left, and back to Route 26.

Traveling Westbound – Route 26 to Central Avenue turn left, to Windmill Drive turn right, and back to Route 26.

Access to all businesses and residences located on both sides of the two culverts will be maintained throughout the duration of the closure. Motorists traveling to areas between the road closures should use the following detour:

Traveling Westbound – Route 26 to Central Avenue turn left, to Cedar Drive turn right, and back to SR 26.

Traveling Westbound to businesses between Central Avenue to BR 3-428 in Ocean View – Proceed west to the left of the diversion barricade through the receiving lane provided on Route 26 at Central Avenue.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between Railway Road and Whites Neck Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 5:00 p.m.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26.

Motorists should anticipate eastbound lane closures on Route 26 between Grants Avenue and Old School Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m.to 5:00 p.m.
Continue the installation of the new sanitary sewer line in Clarksville.

Motorists should anticipate eastbound or westbound lane closures on Route 26 at Powell Farm Road and Omar Road with traffic alternating through the work zone and intersection utilizing a flagging operation by law enforcement and construction personnel from 09:00 a.m. to 5:00 p.m.





+