Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next week.
Monday, December 29, 2014 through Tuesday December 30, 2014
Begin shoulder widening on Route 26, east of Powell Farm Road. Motorists should anticipate lane closures on eastbound Route 26 at Powell Farm Road with traffic alternating through the intersection and through the work zone utilizing a flagging operation by Law Enforcement and construction personnel from 09:00AM to 5:00PM.
Continue the installation of the new sanitary sewer line along Route 26, east and west of Irons Lane. No lane closures are anticipated for this work. Motorists should anticipate periodic short term traffic stoppages as flaggers assist construction vehicles to safely enter and exit the work area from 07:00 a.m. to 5:00 p.m.
Begin work on 48” drainage pipe east of Powell Farm Road. No lane closures are anticipated for this work. Motorists should anticipate periodic short term traffic stoppages as flaggers assist construction vehicles to safely enter and exit the work area from 07:00 p.m. to 5:00 p.m.