Written on: December 1st, 2014 in Route 26
Tuesday, December 2, 2014 through Friday December 5, 2014
Continue installation of the new sanitary sewer line along Route 26 at Route 17 (Roxana Road). Motorists
should anticipate eastbound or westbound lane closures on Route 26 at Route 17 (Roxana Road) with traffic
alternating through the work zone utilizing a flagging operation by law enforcement and construction
personnel between 07:00 a.m. and 5:00 p.m.
Continue install new drainage pipe and associated drainage inlets along Route 26 between Railway Road
and Clubhouse Road. Motorists should anticipate eastbound or westbound lane closures on Route 26
between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a
flagging operation by construction personnel between 07:00 a.m. and 5:00 p.m.
Begin installation of electrical conduits and junction boxes at Central Avenue and Windmill Drive. No
lane closures are anticipated for this work.
Continue paving at Old Mill Road and Route 26. Motorists should anticipate eastbound and westbound
lane shifts on Route 26 and Northbound and Southbound lane shifts on Old Mill Road between 07:00 a.m.
and 5:00 p.m.
……………………………….