route-26

Anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week.

Written on: August 29th, 2014 in Route 26

Tuesday, September 2, 2014 through Friday September 5, 2014

Begin milling and paving of Route 26 between Cedar Drive and Old Mill Road. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Cedar Drive and Old Mill
Road with traffic alternating through the work zone utilizing a flagging operation and with traffic
alternating through the intersection of Route 26 and Old Mill Road utilizing a flagging operation by
law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Begin milling and paving on Cedar Drive south of Route 26. Motorists should anticipate lane
closures on Cedar Drive at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by construction personnel between 7:00 p.m. and 06:00 a.m.

Continue grading for curb and gutter between Grants Avenue and Cedar Drive. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Grants Avenue and Old Mill
Road with traffic alternating through the work zone utilizing a flagging operation as well as lane
closures Old Mill Road at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by law enforcement and construction personnel between 7:00 p.m. and
06:00 a.m.

Continue installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm
Road. No lane closures are anticipated for this construction activity.


route-26

Revised – Anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week. Sunday

Written on: August 25th, 2014 in Route 26

Monday August 25, 2014 through Friday August 29, 2014
Continue milling and paving of Route 26 between Old Mill Road and Grants Avenue. Motorists
should anticipate lane closures on Route 26 between Grants Avenue and Old Mill Road with traffic
alternating through the work zone utilizing a flagging operation as well as lane closures Old Mill
Road at Route 26 with traffic alternating through the intersection utilizing a flagging operation by
law enforcement and construction personnel between 8:00 p.m. and 07:00 a.m.
Begin milling and paving at Cedar Drive and Route 26. Motorists should anticipate lane closures
on Cedar Drive at Route 26 with traffic alternating through the intersection utilizing a flagging
operation by construction personnel between 8:00 p.m. and 07:00 a.m.
Begin grading for curb and gutter between Grants Avenue and Cedar Drive. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Grants Avenue and Old Mill
Road with traffic alternating through the work zone utilizing a flagging operation as well as lane
closures Old Mill Road at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by law enforcement and construction personnel between 8:00 p.m. and
07:00 a.m.
Begin installation of new drainage pipe at Route 26 and Woodland Avenue. Motorists should
anticipate eastbound or westbound lane closures on Route 26 at Woodland Avenue as well as
northbound or southbound lane closures on Woodland Avenue at Route 26 with traffic alternating
through the intersection utilizing a flagging operation.


route-26

Route 26 work schedule

Written on: August 25th, 2014 in Route 26

Due to scheduling conflicts and forecasts for thunderstorms, last weeks’ anticipated construction schedule and associated lane closures did not follow what was advertised by the Construction Management Team.  We apologize the unforeseen changes and for any inconvenience that this may have caused.

Travel times to and from your destination may be quicker if you use one of the Route 26 Alternate Routes that were constructed prior to the start of the SR 26 Mainline Construction Project.  The recently reconstructed roadways include:

Burbage Road, from SR 17 to Windmill Drive

For more information on the Alternate Route Project, visit our website at https://deldot.gov/information/projects/sr26


route-26

Anticipated work schedule and associated lane closures for the SR 26 Mainline Construction Project

Written on: August 14th, 2014 in Route 26

Sunday August 17, 2014 through Friday August 22, 2014

Begin milling and paving at Cedar Drive and Route 26. Motorists should anticipate lane closures
on Cedar Drive and Route 26 with traffic alternating through the intersection utilizing a flagging
operation by law enforcement and construction personnel between 8:00 p.m. and 07:00 a.m.

Begin milling and paving at Old Mill Road and Route 26. Motorists should anticipate lane closures
on Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging
operation by law enforcement and construction personnel between 8:00 p.m. and 07:00 a.m.

Begin grading for curb and gutter between Woodland Avenue and Central Avenue. Motorists
should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and
Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as
well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection
utilizing a flagging operation by law enforcement and construction personnel on Sunday between
10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.

Continue installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm
Road. No lane closures are anticipated for this construction activity.

Continue the installation of Tidewater Utilities, Inc. water line between Grants Avenue and Old
School Lane. Motorists should anticipate eastbound or westbound lane closures on Route 26
between Grants Avenue and Old School Lane with traffic alternating through the work zone
utilizing a flagging operation between 8:00 p.m. and 07:00 a.m.


archaeology-updates

US Route 301 Archaeology Update

Written on: August 14th, 2014 in Archaeology UpdatesUS301

Osteological and Ancient DNA Analyses of Burials from the Elkins Site (7NC-G-174) Completed

Five burials (A, B, C, D and G) were excavated at the Elkins Site (7NC-G-174) in late September and early October of 2012 by Hunter Research, Inc. The osteological and ancient DNA analyses of the four adults and one infant have been completed by skeletal biologists and an anthropological geneticist at the University of Montana.

Of the four adults (Burials B, C, D and G), two were male and two were female. Ancient DNA analysis of the amelogenin gene indicates that the 2- to 5-month-old infant (Burial A) was male. These results are exciting as sex of this infant could not have been estimated from the skeletal remains. The table below presents an overview of the human skeletal remains from this site.

Elkins Burials

Results of the mitochondrial DNA analysis (which traces maternal genetic lineages) classifies all five individuals as having European maternal ancestry. Interestingly neither of the adult females were the mother of the young infant, but the elderly male from Burial D shares the same mitochondrial DNA mutations suggesting that they are maternally related.

All of the adults show evidence for rigorous physical activity, and the older individuals suffered from osteoarthritis to varying degrees. The elderly male in Burial D was particularly affected by degenerative changes to his skeleton with fusion of multiple vertebrae in his neck and lower back due to extensive bony growths. The anterior joint of his pelvis, the pubic symphysis, was also completely fused and evidence for degenerative joint disease was found across his body. He had also suffered from a broken nose, a broken rib and a broken foot bone during life!

Dental health among these individuals was not particularly good. All adults had lost teeth during life and many of the teeth that remained had small to large cavities. Both adult males had pipe stem facets/grooves in the teeth of both males from clenching a pipe stem in the mouth. Chipping of the chewing edge of the canines was observed on the female of Burial G, suggesting she held hard objects such as straight pins between her teeth.

 

Burial C teeth with closeup of pipe stem groove (right).

Burial C teeth with closeup of pipe stem groove (right).

Burial D with close up of pipe stem grooves (right).

Burial D with close up of pipe stem grooves (right).


route-26

Anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week.

Written on: August 11th, 2014 in Route 26

Sunday August 10, 2014 through Friday August 15, 2014

Continue installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm
Road. No lane closures are anticipated for this construction activity.

Continue milling and paving of Route 26 between Central Avenue and West Avenue. Motorists
should anticipate eastbound or westbound lane closures along Route 26 between West Avenue and
Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as
well as traffic alternating through the signalized intersections utilizing a flagging operation by
law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and
Monday through Thursday between 8:00 p.m. and 07:00 a.m..

Continue installation of new drainage system between Woodland Avenue and West Avenue.
Motorists should anticipate eastbound or westbound lane closures on Route 26 between West
Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging
operation as well as alternating through the signalized intersections utilizing a flagging operation
by law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and
Monday through Thursday between 8:00 p.m. and 07:00 a.m.


route-26

Anticipated work schedule and associated lane closures for the SR 26 Mainline Construction Project

Written on: August 1st, 2014 in Route 26

Sunday, August 3 through Friday, August 8.

Begin installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm Road.  No lane closures are anticipated for this construction activity.

Continue milling and paving of Central Avenue, north of Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday from 10:30 p.m. until 7 a.m. on Monday; and Monday evening through Friday morning from 8 p.m. until 7 a.m.

Continue installation of new drainage system between Woodland Avenue and West Avenue.

Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Avenue with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday from 10:30 p.m. until 7 a.m. Monday; and Monday evening through Friday morning from 8 p.m. until 7 a.m.

Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging on Sunday from 10:30 p.m. until 7 a.m. Monday; and Monday evening through Friday morning from 8 p.m. until 7 a.m.

Continue excavation of Storm Water Management Pond #332 located west of Route 17/Roxana Road and Storm Water Management Pond #333 located at Windmill Drive and Route 26.  No lane closures are anticipated for these construction activities.





+