Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next two weeks.

Written on: June 20th, 2014 in Route 26

Monday June 23, 2014 through Friday June 27, 2014

Continue reconstruction of the Central Avenue/Route 26 intersection.  Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue reconstruction of the Old Mill Road/Route 26 intersection.  Motorists should anticipate   lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue work on the installation of the new drainage system between Cedar Drive and Old School Lane.  Motorists should anticipate the eastbound or westbound lane of Route 26 between Old Mill Road and Old School Lane to be closed with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.

Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day.  No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #331 located west of Irons Lane.  No lane closures are anticipated for this work.

Begin water main relocation work between Woodland Avenue and Central Avenue.  Motorist should anticipate shoulder closures along Route 26 from Woodland Avenue to Central Avenue between 7:00 p.m. and 06:00 a.m. 

Monday June 30, 2014 through Thursday July 3, 2014

Continue water main relocation work between Woodland Avenue and Central Avenue.  Motorist should anticipate shoulder closures along Route 26 from Woodland Avenue to Central Avenue between 7:00 p.m. and 06:00 a.m. 

Continue reconstruction of the Old Mill Road/Route 26 intersection. Motorists should anticipate lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue work on the installation of the new drainage system between Old Mill Road and Clubhouse Road.  Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Old Mill Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.

Continue reconstruction of the Central Avenue/Route 26 intersection.  Motorists should anticipate eastbound or westbound lane closures on Route26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day.  No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #331 located west of Irons Lane.  No lane closures are anticipated for this work.

 




+