Route 26 Scheduled Lane Closures

Written on: June 12th, 2014 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next two weeks.

 Monday June 16, 2014 through Friday June 20, 2014

 Continue reconstruction of the Central Avenue/Route 26 intersection.  Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Avenue with traffic alternating through the work zone utilizing a flagging operation between 07:00 p.m. and 6:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00 p.m. and 6:00 a.m.

 Continue reconstruction of the Old Mill Road/Route 26 intersection.  Motorists should anticipate   lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00 p.m. and 6:00 a.m.

Continue work on the installation of the new drainage system between Cedar Drive and Old School Lane.  Motorists should anticipate the eastbound or westbound lane of Route 26 between Old Mill Road and Old School Lane to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00 p.m. and 6:00 a.m.

 Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day.  No lane closures are anticipated for this work.

 Continue excavation of Storm Water Management Pond #331 located west of Irons Lane.  No lane closures are anticipated for this work.

 Monday June 23, 2014 through Friday June 27, 2014

 Continue reconstruction of the Old Mill Road/Route 26 intersection. Motorists should anticipate lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00 p.m. and 6:00 a.m.

 Continue work on the installation of the new drainage system between Grants Avenue and Woodland Avenue.  Motorists should anticipate the eastbound or westbound lane of Route 26 between Old Mill Road and Woodland Avenue to be closed with traffic alternating through the work zone utilizing a flagging operation between 07:00 p.m. and 6:00 a.m.

 Continue excavation of Storm Water Management Pond #332 located east of Route17 (Roxana Road) during the day.  No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #331 located west of Irons Lane.  No lane closures are anticipated for this work.




+