Indian River Inlet Bridge – Update

Written on: December 30th, 2011 in Indian River Inlet Bridge

Finishing activities continue as the work progresses towards a January 2012 opening to traffic.  Some of the primary activities remaining to be performed prior to opening include: deck surface grinding and grooving, pavement striping, final stay tensioning adjustments, stay damper installation, pylon work platform removal, tower crane removal and final punchlist work.  Some additional work activities will continue after the initial opening to traffic.  These include: electrical work, aesthetic lighting installation, sand bypass system installation, future northbound barrier rail installation, pedestrian walkway lighting, painting, and a final detailed inventory inspection. 





+