Written on: September 26th, 2011 in Route 54
Night work operations were extended through the month of September. Day work is expected to resume on October 3. The contractor continues placement of the new drainage pipe. A few remaining pipe runs cannot be completed due to conflicts with Verizon utilities. Once the relocation is performed the drainage system will be completed. The hot-mix wedging and shoulder overlay is complete on the north side of the road. This work was necessary to insure the shoulder can accommodate traffic as we shift the travel lanes for Phase 2.