Written on: September 26th, 2011 in I95/SR1 Interchange
Limited work activities such as clearing, and installation of erosion and sediment control measures
Christiana Mall Rd. Bridge: The pier and abutment wall work is complete and waiting for the steel girders to be delivered (Scheduled to be delivered on 9/27/11). Other activities such as roadway construction and bridge painting activities continue as well. We are working with Mall management to mitigate traffic impacts from the project for the upcoming holiday season.