Written on: May 23rd, 2011 in I-95 I95/SR1 Interchange
The contractor is continuing to aggressively pursue work on the project by working seven days a week. Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and sheet pile installation for the Christiana Mall pond should begin by the end of the week. The contractor has placed the concrete for one abutment wall and will complete the backwall this week. Form work for the wingwalls should begin this week. Within the next few weeks, rehabilitation work on the I-95 bridges over SR 1 will begin. Work is scheduled to be complete on this project at the end of the year.