Written on: April 21st, 2011 in Elkton Road
A value engineering proposal (VEP) has been proposed to and accepted by the Department to allow the contractor to enter into Phase III traffic pattern earlier than planned. The proposal allows the contractor an alternate method to install the new water main. The VEP change will save DelDOT money and will give the contractor a better chance to complete the Phase Three work before the beginning of the University of Delaware’s fall semester. Work is scheduled to be complete in December 2012.