DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

  Archived Posts From: 2016

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: September 9th, 2016 in US 301 Project UpdatesUS301

Friday, September 9, 2016 to Monday, September 12, 2016

Temporarily close Summit Bridge Road (U.S. Route 301) between Marl Pit Road and Old School House Road on Friday, September 9, 2016, at 8:00 p.m. through Monday, September 12, 2016, at 5:00 a.m. for the installation of a pre-cast box culvert. This closure will detour traffic to Boyd’s Corner Road (Route 896), to U.S. Route 13, to Marl Pit Road and back to Summit Bridge Road.


Monday, September 12, 2016 through Friday, September 16, 2016 – Dayshift

Continue installing temporary concrete barrier wall along existing southbound U.S. Route 301 between Merrimac Road and Levels Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m.

Begin relocating ITMS conduit along southbound State Route 1. Motorists should anticipate single lane closures on southbound State Route 1 between the Roth Bridge and the Toll Plaza from 9 a.m. to 3 p.m.

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.

Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.

Tuesday, September 13, 2016 through Thursday, September 15, 2016 – Nightshift

Continue setting temporary concrete barrier wall northbound and southbound State Route 1 in the median, south of the Roth Bridge. Motorists should anticipate northbound and southbound left lane closures along State Route 1 from the Roth Bridge to south of Biddles Toll Plaza from 7:00 p.m. to 6:00 a.m.


us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: September 6th, 2016 in US 301 Project UpdatesUS301

Tuesday, September 6, 2016 through Friday, September 10, 2016 – Dayshift

Continue preparations for box culvert construction on Summit Bridge Road. Motorists should anticipate a right shoulder closure on northbound Summit Bridge Road, north of Marl Pit Road from 7:00 a.m. – 5:00 p.m.

Continue installing temporary concrete barrier wall along existing southbound US 301 between Merrimac Road and Levels Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m.

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.

Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.

Tuesday, September 6, 2016 through Thursday, September 8, 2016 – Nightshift

Continue setting temporary concrete barrier wall northbound and southbound State Route 1 in the median, south of the Roth Bridge. Motorists should anticipate northbound and southbound left lane closures along State Route 1 from the Roth Bridge to south of Biddles Toll Plaza from 7:00 p.m. to 6:00 a.m.

Friday, September 9, 2016 to Monday, September 12, 2016

Temporarily close Summit Bridge Road (U.S. Route 301) between Marl Pit Road and Old School House Road on Friday, September 9, 2016, at 8:00 p.m. through Monday, September 12, 2016, at 5:00 a.m. for the installation of a pre-cast box culvert. This closure will detour traffic to Boyd’s Corner Road (Route 896), to U.S. Route 13, to Marl Pit Road and back to Summit Bridge Road.





+