SR141/I-95 Ramp Interchange Project December 23, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project December 16, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. This week, beam installation will begin on SR141 southbound and the placement of storm […]


Read More

Tuesday, January 3 through Thursday, January 5

Written on: December 29th, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, January 3 through Friday, January 6 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate […]


Read More

Tuesday, December 27 through Thursday, December 29

Written on: December 23rd, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along southbound SR 1 between the Roth Bridge and Toll Plaza. Tuesday, December 27 through Friday, December 30 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: December 16th, 2016 in US 301 Project UpdatesUS301

Sunday, December 18, 2016 through Friday, December 23, 2016 Strawberry Lane will be closed to traffic at U.S. Route 301 on December 19, 2016 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: December 13th, 2016 in SR141

SR141/I-95 Ramp Interchange Project December 2, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: December 13th, 2016 in SR141

SR141/I-95 Ramp Interchange Project November 18, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: December 9th, 2016 in US 301 Project UpdatesUS301

Sunday, December 11, 2016 through Saturday, December 17, 2016 Begin placing concrete for new bridge pier along southbound State Route 1. Motorists should anticipate single lane closures on southbound State Route 1 between the Roth Bridge and the Toll Plaza from 9 a.m. to 3:00 p.m. Continue removing existing pipe culvert along Port Penn Road, […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: November 23rd, 2016 in US 301 Project UpdatesUS301

Tuesday, November 29, 2016 through Saturday, December 3, 2016 Begin hauling activities Summit Bridge Road at night. Motorists should anticipate the following nightly closures of Summit Bridge Road: • Monday night, November 28, from 8:00 p.m. through 5:00 a.m. • Tuesday night, November 29, from 8:00 p.m. through 5:00 a.m. • Wednesday night, November 30, […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: November 18th, 2016 in US 301 Project UpdatesUS301

Sunday, November 20, 2016 through Tuesday, November 22, 2016 Begin setting temporary concrete barrier on Summit Bridge Road, north of Armstrong Corner Road on Sunday, November 20, 2016. Motorists should anticipate a southbound lane closure on Summit Bridge Road, north of Armstrong Corner Road with traffic alternating through the work zone utilizing a flagging operation […]