Below is an outline of the anticipated construction schedule and associated lane closures for work on the US301 Mainline Project during the next week.

Written on: March 23rd, 2017 in US 301 Project UpdatesUS301

Monday, March 27, 2017 through Thursday, March 30, 2017 Continue bridge construction activities along SR1. Motorists should anticipate single lane closures along northbound or southbound SR1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Monday, March 20, 2017 through Friday, March 31, 2017 Continue preliminary construction activities for roadway widening […]


Read More

Below is an outline of the REVISED anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: March 20th, 2017 in US 301 Project UpdatesUS301

Friday, March 17, 2017 through Monday, March 20, 2017 U.S. Route 13 will be closed to through between Hyetts Corner Road and Port Penn Road from 7:00 p.m. on Friday, March 17, 2017 through Monday, March 20, 2017 at 5:00 a.m. This closure will detour traffic to Pole Bridge Road, to Port Penn Road and […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: March 16th, 2017 in US 301 Project UpdatesUS301

Friday, March 17, 2017 through Monday, March 20, 2017 U.S. Route 13 will be closed to through between Hyetts Corner Road and Port Penn Road from 7:00 p.m. on Friday, March 17, 2017 through Monday, March 20, 2017 at 5:00 a.m. This closure will detour traffic to Pole Bridge Road, to Port Penn Road and […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: March 9th, 2017 in US 301 Project UpdatesUS301

Monday, March 13, 2017 through Thursday, March 16, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Monday, March 13, 2017 through Friday, March 17, 2017 Begin median reconstruction […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for the week of March 6.

Written on: March 3rd, 2017 in US 301 Project UpdatesUS301

Monday, March 6 through Thursday, March 9. Continue bridge construction activities along SR 1. Motorists should anticipate single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Monday, March 6 through Friday, March 10. Continue dirt hauling and bridge construction activities on Boyd’s […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 24th, 2017 in US 301 Project UpdatesUS301

Monday, February 27, 2017 through Thursday, March 2, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Tuesday, February 28, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the this week.

Written on: February 20th, 2017 in US 301 Project UpdatesUS301

Monday, February 20, 2017 through Thursday, February 23, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Tuesday, February 21, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 17th, 2017 in US 301 Project UpdatesUS301

Monday, February 20, through Thursday, February 23 Continue bridge construction activities along SR 1. Motorists should anticipate single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, February 21, 2017 motorists should anticipate a single lane closure along southbound SR 1 with periodic […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 10th, 2017 in US 301 Project UpdatesUS301

Monday, February 13, 2017 through Thursday, February 16, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Thursday, February 16, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: February 6th, 2017 in US 301 Project UpdatesUS301

Monday, February 6, 2017 through Thursday, February 9, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Begin installing roadway light pole bases. Motorists should anticipate northbound and southbound […]