Below is an outline of the anticipated construction schedule and associated lane closures for the week of March 6.

Written on: March 3rd, 2017 in US 301 Project UpdatesUS301

Monday, March 6 through Thursday, March 9. Continue bridge construction activities along SR 1. Motorists should anticipate single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Monday, March 6 through Friday, March 10. Continue dirt hauling and bridge construction activities on Boyd’s […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 24th, 2017 in US 301 Project UpdatesUS301

Monday, February 27, 2017 through Thursday, March 2, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Tuesday, February 28, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the this week.

Written on: February 20th, 2017 in US 301 Project UpdatesUS301

Monday, February 20, 2017 through Thursday, February 23, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Tuesday, February 21, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 17th, 2017 in US 301 Project UpdatesUS301

Monday, February 20, through Thursday, February 23 Continue bridge construction activities along SR 1. Motorists should anticipate single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, February 21, 2017 motorists should anticipate a single lane closure along southbound SR 1 with periodic […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: February 10th, 2017 in US 301 Project UpdatesUS301

Monday, February 13, 2017 through Thursday, February 16, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Thursday, February 16, 2017 motorists should anticipate a single lane closure along […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: February 6th, 2017 in US 301 Project UpdatesUS301

Monday, February 6, 2017 through Thursday, February 9, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Begin installing roadway light pole bases. Motorists should anticipate northbound and southbound […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: January 27th, 2017 in US 301 Project UpdatesUS301

Monday, January 30, 2017 through Thursday, February 2, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Begin installing roadway light pole bases. Motorists should anticipate northbound and southbound […]


Read More

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: January 20th, 2017 in US 301 Project UpdatesUS301

Tuesday, January 24 through Thursday, January 26 Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Monday, January 23 through Friday, January 27 Continue installing ITMS along the right shoulder of […]


Read More

Tuesday, January 3 through Thursday, January 5

Written on: December 29th, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, January 3 through Friday, January 6 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate […]


Read More

Tuesday, December 27 through Thursday, December 29

Written on: December 23rd, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along southbound SR 1 between the Roth Bridge and Toll Plaza. Tuesday, December 27 through Friday, December 30 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route […]


Read More