Written on: September 8th, 2017 in US 301 Project Updates US301
Monday, September 11, 2017 through Thursday, September 14, 2017
Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.
Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 9:00 a.m. to 3:00 p.m.
Continue roadway widening activities along southbound US 13. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 9:00 a.m. to 2:00 p.m.
Monday September 11, 2017 through Thursday, September 14, 2017 – Nightshift
Continue bridge construction activities along SR 1. Motorists should anticipate a single left lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 9:00 p.m. to 6:00 a.m.
Detours and Roadway Closures
Northbound US 13 between Hyetts Corner Road and Port Penn Road will be closed on Friday, September 8, at 7 p.m. through Monday, September 11, at 6 a.m. This closure will detour traffic to Pole Bridge Road, to Port Penn Road and back to US 13. Truck traffic will be urged to use SR 1 as the alternate route for through traffic to points north.
Southbound SR 1 will be closed on Wednesday, September 13, from 9 p.m. to 5 a.m. between the Roth Bridge and Pole Bridge Road. Motorists are advised to follow the posted detour of Lorewood Grove Road (Exit 148) to US 13 south to Pole Bridge Road and back to SR 1.
Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US 13. Traffic accessing Port Penn Road from southbound US 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US 13 will follow US 13 to the traffic signal at the free ramp to northbound SR 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect until June 2018 after the intersection is reconstructed and the new traffic signal becomes operational.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyett’s Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road (SR 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.
Strawberry Lane is closed to traffic at US 301. Motorists wanting to access the east side of Strawberry Lane from US 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from US 301 will turn left onto the new Levels Road-Middletown/Warwick Road (SR 299) and follow Middletown-Warwick Road (SR 299) to Strawberry Lane.