sr141

SR141/I95 Ramp Interchange Project

Written on: July 11th, 2017 in SR141

R141/I-95 Ramp Interchange Project
June 30, 2017

The contractor, Mumford & Miller Inc., will continue placing fill for widening I-95 northbound acceleration lane from SR 141. They will continue to form and pour barrier for SR 141 northbound. They are working on installing utility infrastructure through the SR 141 and I-95 northbound corridor. The contractor is reconstructing the ramp for Exit 3A, northbound SR141 to northbound I-95. They are installing a stormwater drainage system on this ramp. The contractor has begun clearing vegetation on SR 141 Southbound on the closed side of the roadway.

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Thursday thru Friday.

Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late October 2017. northbound SR141/Newport should use Exit 5.