DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project for the week of May 30.

Written on: May 25th, 2017 in US 301 Project Updates US301

Tuesday, May 30 through Thursday, June 1- Nightshift

Continue bridge construction for US 301 over Boyds Corner Road (SR 896). Motorists should anticipate a single lane closure with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 p.m. until 6 a.m.

Wednesday, May 31 through Thursday, June 1

Continue repainting of temporary concrete barrier wall along US Route 13, south of the on ramp to State Route 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for State Route 1 from 9 a.m. until 3 p.m.

Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 p.m.

Motorists should anticipate northbound or southbound lane closures on Summit Bridge Road, south of the Armstrong Corner Road/Marl Pit Road intersection, with traffic alternating through the work zone and intersection utilizing a flagging operation by law enforcement and construction personnel from 09:00 a.m. to 3:00 p.m.
Please adjust your travel schedule accordingly as this lane closure may have an impact on travel times to and from your intended destination.

Wednesday, May 31 through Friday, June 2

Continue roadway reconstruction along existing US 301 at Levels Road. Motorists should anticipate northbound and southbound single lane closures on existing US 301 at Levels Road from 8 a.m. until 4 p.m.

Continue dirt hauling and bridge construction activities across Summit Bridge Road. Motorists should anticipate a flagging operation by construction personnel on Summit Bridge Road near North of Marl Pit Road/Armstrong Corner Road from 7 a.m. until 5 p.m.

Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7 a.m. until 5 p.m.

Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US Route 13. Traffic accessing Port Penn Road from southbound US 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US 13 will follow US 13 to the traffic signal at the free ramp to northbound State Route 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect until June 2018 after the intersection is reconstructed and the new traffic signal becomes operational.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road.  Motorists traveling eastbound on Hyett’s Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road (SR 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.

Middle Neck Road is closed at US 301. Motorists wishing to access Middle Neck Road from US 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.

Strawberry Lane is closed to traffic at US 301. Motorists wanting to access the east side of Strawberry Lane from US 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from US 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.

 




+