DelDOT logo
DelDOT Blog


Delaware Department of Transportation


        

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: April 20th, 2017 in US 301 Project Updates US301

Monday, April 24, 2017 through Thursday, April 27, 2017

Continue bridge construction activities along SR 1. Motorists should anticipate a single lane closures along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m.
Continue repainting of temporary concrete barrier wall along US 13 south of the on ramp to SR 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for SR 1 from 9:00 a.m. to 3:00 p.m.

Monday, April 24, 2017 through Friday, April 28, 2017

Continue roadway drainage pipe installation along Summit Bridge Road. Motorists should anticipate northbound or southbound lane closures on Summit Bridge Road, north and south of the Armstrong Corner Road/Marl Pit Road intersection, with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 09:00 a.m. to 3:00 p.m.
Continue paving activities along existing US 301 at Levels Road. Motorists should anticipate southbound right lane closures on existing US 301 at Levels Road from 8:00 a.m. to 4:00 p.m..
Continue installing light pole bases along the northbound and southbound shoulder of US 13 between Old Hyetts Corner Road and Port Penn Road. Motorists should anticipate a northbound and southbound right shoulder closure along US 13 between Old Hyetts Corner Road and Port Penn Road from 9:00 a.m. to 3:00 p.m.
Continue dirt hauling and bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road (SR 896) west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US 13. Traffic accessing Port Penn Road from southbound US 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US 13 will follow US 13 to the traffic signal at the free ramp to northbound SR 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect until June 2018 after the intersection is reconstructed and the new traffic signal becomes operational.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyett’s Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road (SR 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.
Middle Neck Roads is closed at US 301. Motorists wishing to access Middle Neck Road from US 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at US 301. Motorists wanting to access the east side of Strawberry Lane from US 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from US 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.

Wednesday, April 26, 2017 – Nightshift

Motorists can expect double lane closures along southbound SR 1 between the Roth Bridge and the Toll Plaza to move equipment from the right shoulder to the median from 10:00 p.m. to 5:00 a.m.




Navigation



Adjust Your Font Size


Make Text Size Smaler Reset Text Size Make Text Size Bigger




+