Sunday, December 18, 2016 through Friday, December 23, 2016
Strawberry Lane will be closed to traffic at U.S. Route 301 on December 19, 2016 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.
Begin installing temporary concrete barrier on existing U.S. Route 301 from the Maryland Line to Strawberry Lane. Motorists should anticipate a northbound or southbound lane closure on existing U.S. Route 301 between the Maryland Line and Strawberry Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 a.m. to 3:00 p.m.
Continue installing ITMS along the right shoulder of southbound State Route 1. Motorists should anticipate a right shoulder closure along southbound state Route 1 between the Roth Bridge and Toll Plaza.
Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route 13 between Old Hyetts Road and Port Penn Road from 9:00 a.m. to 3:00 p.m.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Middle Neck Road is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.