DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: May 31st, 2016 in US 301 Project Updates US301

Tuesday, May 31, 2016 through Saturday, June 4, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00A a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Continue excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High School. No lane closures are needed for this construction activity.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Continue hauling activities across Middleneck road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 4:00 p.m.