DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

  Archived Posts From: 2016

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: May 5th, 2016 in US 301 Project UpdatesUS301

Monday, May 9, 2016 through Saturday, May 14, 2016

Continue dirt hauling activities along Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Continue excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High School. No lane closures are needed for this construction activity.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 9:00 a.m. to 3:00 p.m.

Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 4:00 p.m.





+