Route 26 Mainline Improvement Project Scheduled Lane Closures

Below is an outline of the anticipated construction schedule and associated lane closures for work on the Route 26 Mainline Improvement Project during the next week. Please note that the
first construction activity listed will take place at night.

Monday, April 27, 2015 through Saturday May 2, 2015

Begin milling and paving activities along Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between Cedar Drive and Woodland Avenue with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 p.m. to 6:00 a.m.

Continue underground utility relocations in Ocean View. Motorists should anticipate lane shifts on Route 26 between West Avenue and Tyler Drive with both lanes getting through the work zone. This lane shift will be in place 24 hours a day, seven days a week.

Continue the installation of new drainage pipe and associated drainage inlets along Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between
Woodland Avenue and Old School Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 06:00 a.m. to 6:00 p.m.

Continue placing concrete for new sidewalks along Route 26. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Central Avenue and Woodland
Avenue with both lanes getting through the work zone from 6:00 a.m. to 6:00 p.m..

Continue placing concrete for new sidewalks along Route 26. Motorists should anticipate eastbound and westbound lane shifts on Route 26 between Old Mill Road and Cedar Drive with
both lanes getting through the work zone from 6:00 a.m. to 6:00 p.m.

Begin adjusting manholes along Route 26. Motorists should anticipate eastbound and westbound lane closures on Route 26 between Whites Neck Road and Windmill Drive with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 6:00 a.m. to 6:00 p.m..

Continue adjusting manholes along Route 26. Motorists should anticipate eastbound and westbound lane closures on Route 26 between Club House Road and Dukes Drive with traffic
alternating through the work zone utilizing a flagging operation by construction personnel from 06:00 a.m. to 6:00 p.m.

Continue grading prior to placement of curb and gutter along Route 26. Motorists should anticipate eastbound and westbound lane closures on Route 26 between Club House Road and Dukes Drive with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 6:00 a.m. to 6:00 p.m.

Continue cleanup and placing topsoil between the new sidewalks and curb along Route 26.

Motorists should anticipate eastbound or westbound lane shifts on Route 26 between Grants Avenue and Cedar Drive with both lanes getting through the work zone from 6:00 a.m. to 6:00 p.m.




+