Anticipated construction schedule and associated lane closures for work on and within the Route 26 Widening Project during the next week

Written on: September 12th, 2014 in Route 26

Sunday, September 14, 2014

Continue the installation of the privately owned Tidewater Utilities, Inc. water line between
Grants Avenue and Old School Lane. Motorists should anticipate eastbound or westbound lane
closures on Route 26 between Grants Avenue and Old School Lane with traffic alternating through
the work zone utilizing a flagging operation between 10:300 p.m. and 06:00 a.m.

Begin grading for curb and gutter at Route 26 and Docs Place. Motorists should anticipate
westbound lane closures on Route 26 between Old Mill Road and Cedar Drive with traffic
alternating through the work zone utilizing a flagging operation by construction personnel
between 10:300 p.m. and 06:00 a.m.

Monday, September 15, 2014 through Friday September 19, 2014

Continue milling and paving between Old Mill Road and Cedar Drive. Motorists should
anticipate westbound lane closures on Route 26 between Old Mill Road and Cedar Drive with
traffic alternating through the work zone utilizing a flagging operation as well as traffic
alternating through the intersection utilizing a flagging operation by law enforcement and
construction personnel between 7:00 p.m. and 06:00 a.m.




+