DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

route-26

Anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next week.

Written on: August 29th, 2014 in Route 26

Tuesday, September 2, 2014 through Friday September 5, 2014

Begin milling and paving of Route 26 between Cedar Drive and Old Mill Road. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Cedar Drive and Old Mill
Road with traffic alternating through the work zone utilizing a flagging operation and with traffic
alternating through the intersection of Route 26 and Old Mill Road utilizing a flagging operation by
law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Begin milling and paving on Cedar Drive south of Route 26. Motorists should anticipate lane
closures on Cedar Drive at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by construction personnel between 7:00 p.m. and 06:00 a.m.

Continue grading for curb and gutter between Grants Avenue and Cedar Drive. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Grants Avenue and Old Mill
Road with traffic alternating through the work zone utilizing a flagging operation as well as lane
closures Old Mill Road at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by law enforcement and construction personnel between 7:00 p.m. and
06:00 a.m.

Continue installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm
Road. No lane closures are anticipated for this construction activity.




+