Written on: July 18th, 2014 in Route 26
Sunday July 20, 2014 through Thursday July 24, 2014
Begin driving sheet piles at the southwest corner of Route 26/Cedar Drive for construction of new modular retaining wall. No lane closures are anticipated for this construction activity.
Continue work on the installation of the new drainage system between Railway Road and Windmill Drive. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue installation of new drainage system between Woodland Avenue and West Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue excavation of Storm Water Management Pond #332 located west of Route 17 (Roxana Road) and Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for these construction activities.
Sunday July 27, 2014 through Thursday July 31, 2014
Begin installation of well points along the south side of Route 26 for sanitary sewer line expansion, west of Irons Lane. No lane closures are anticipated for these construction activities.
Continue driving sheet piles at the southwest corner of Route 26/Cedar Drive for construction of new modular retaining wall. No lane closures are anticipated for this construction activity.
Continue work on the installation of the new drainage system between Railway Road and Windmill Drive. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue installation of new drainage system between Woodland Avenue and West Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue excavation of Storm Water Management Pond #332 located west of Route 17 (Roxana Road) and Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for these construction activities.