The anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next two weeks.

Written on: June 30th, 2014 in Route 26

Monday June 30, 2014 through Thursday July 3, 2014

 Begin minor grading activities at Omar Road and Route 26. No lane closures are anticipated for this work.

 Begin excavation of Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for this work.

 Continue reconstruction of the Central Avenue/Route 26 intersection and water main relocation work between Woodland Avenue and Central Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

 Continue work on the installation of the new drainage system between Old Mill Road and Clubhouse Road. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Old Mill Road and Wind Mill Drive with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.

 Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day. No lane closures are anticipated for this work.

 Continue reconstruction of the Old Mill Road/Route 26 intersection. Motorists should anticipate lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

 Monday July 7, 2014 through Friday July 11, 2014

 Continue minor grading activities at Omar Road and Route 26. No lane closures are anticipated for this work.

 Continue excavation of Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for this work.

 Continue reconstruction of the Central Avenue/Route 26 intersection and water main relocation work between Woodland Avenue and Central Avenue.   Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m. 

Continue work on the installation of the new drainage system between Old Mill Road and Windmill Drive. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Old Mill Road and Wind Mill Drive with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. 

Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day. No lane closures are anticipated for this work.




+