DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

route-26

Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Widening Project during the next two weeks.

Written on: May 22nd, 2014 in Route 26

Tuesday May 27, 2014 through Friday May 30, 2014

 Continue work on the installation of the new drainage system between Old Mill Road and Grants Avenue.  Motorists should expect the eastbound or westbound lane of SR 26 to be closed between Old Mill Road and Grants Avenue with traffic alternating utilizing a flagging operation between 07:00PM and 6:00AM.

 Begin reconstruction of the Old Mill Road/SR 26 intersection. Motorists should expect lane closures on Old Mill Road at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

 Begin work on installation of new Sussex County Sewer line between the Millville Town Limits and Powell Farm Road.  Motorists should expect the eastbound or westbound lane of SR 26 to be closed between SR 17 (Roxana Road) and Whites Neck Road with traffic alternating utilizing a flagging operation between 07:00PM and 6:00AM.

 Continue excavation of Storm Water Management Pond #332 located east of SR 17 (Roxana Road).  No lane closures are anticipated for this work.

 Monday June 2, 2014 through Friday June 6, 2014

 Continue work on the installation of new drainage system between Old Mill Road and Grants Avenue.  Motorists should expect the eastbound or westbound lane of SR 26 between Old Mill Road and Grants Avenue to be closed with traffic alternating utilizing a flagging operation between 07:00PM and 6:00AM.

 Continue reconstruction of the Old Mill Road/SR 26 intersection. Motorists should expect lane closures on Old Mill Road at SR 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 07:00PM and 6:00AM.

 Continue installation of the new Sussex County Sewer Line between the Millville Town Limits and Powell Farm Road.  Motorists should expect the eastbound or westbound lane of SR 26 to be closed in the area of SR 17 (Roxana Road) with traffic alternating utilizing a flagging operation between 07:00PM and 6:00AM.

 Continue excavation of Storm Water Management Pond #332 located east of SR 17 (Roxana Road).  No lane closures are anticipated for this work.




+