Indian River Inlet Bridge – Update

December 12th, 2011

Indian River Inlet Bridge - November 2011

Several finishing activities continue as the work progresses towards a January 2012 opening to traffic.  The concrete bridge barriers are complete and the new polyester polymer concrete (PPC) deck overlay work is on-going.  Bridge electrical and lighting work continues, but is not critical for the bridge opening.  Final tensioning adjustments and damper installation work also continues for the cable stay system.