Facebook Twitter Flickr YouTube RSS Feed
Written on: April 21st, 2011 in I-95 I-95 Delaware Toll Plaza
Final surface paving of available southbound areas, south of the plaza is scheduled to begin Monday night, April 18, using progressive single and double lane closures (all lanes). Double lanes closures cannot begin until 11 PM. Installations of northbound overhead sign structure trusses between the Maryland state line and the toll plaza are rescheduled to begin Wednesday night, April 27 (next week), but may be postponed if paving work is ongoing. This work involves double lane closures from 11 PM to 5 AM with short term rolling roadblocks. The project is scheduled for completion in August 2011.
For more information, please visit the project page by clicking here.