DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

i-95

I-95 Delaware Toll Plaza Project – Update

Written on: March 22nd, 2011 in I-95 I-95 Delaware Toll Plaza

Work continues at the toll plaza as glass panels are placed for the exterior facing of the new overhead walkway.  The roadwork construction continues in the Northbound and Southbound direction for the new inside High Speed EZ Pass lanes, as well as the outside approach roadway reconstruction leading to the toll plaza. The contractor maintains three lanes of traffic, as well as seven toll lanes in each direction during peak hours of operation.  Daytime lane closures during off peak hours, 9 am to 3 pm, during weekdays and weekends are permitted for work on the overhead walkway and gantry systems. The project is scheduled to be completed by August 2011. 

For more information, please visit the project page by clicking here.




+